Summary
You can provide overrides to the baseline lead time settings in StockIQ via the Lead Time Overrides screen.
This screen is accessed by clicking Admin --> System Configuration --> Lead Time Overrides
Add a new override by clicking the "+" button in the grid.
Multiple overrides at once can be uploaded using the "Upload..." button at the top of the screen.
*Note: Item-site overrides take precedence over Supplier-Site overrides
Column Description
By selecting either the "Item Site Supplier" or "Supplier Site" tab, you can choose to enter an override for either a specific item-site-supplier combination, or for all items sourced from a given supplier into a given site. In either case, fill in the desired site, supplier (and item), and then select from the remaining parameters:
- Admin LT: This is the method by which Admin LT will be chosen. (See method descriptions below)
- Mfr LT: The method by which Manufacturing LT will be chosen . (See method descriptions below)
- Shipping LT: The method by which Shipping LT will be chosen . (See method descriptions below)
- Putaway LT: The method by which Putaway LT will be chosen . (See method descriptions below)
- Admin LT Fixed Value: the fixed lead time value to use for Admin LT, if using the "Fixed Value" method
- Mfr LT Fixed Value: the fixed lead time value to use for Manufacturing LT, if using the "Fixed Value" method
- Shipping LT Fixed Value: the fixed lead time value to use for Shipping LT, if using the "Fixed Value" method
- Putaway LT Fixed Value: the fixed lead time value to use for Putaway LT, if using the "Fixed Value" method
Lead Time Selection Methods
For each of the components of lead time in your override, you can select the method by which StockIQ will select the lead time to use. The values are:
- Host Provided: Use the value provided from the host ERP system. If no value is present, defaults in the Global Lead Time Settings will be used.
- Calculated: Use the calculated value from StockIQ based on your receipt history etc. If insufficient receipt history is available, then the ERP lead time will be used. If no ERP LT is available, Global defaults will be used.
- Host Value When Provided: This will use the ERP lead time if provided, but will fall back on StockIQ's lead time if the value from the ERP is null. If neither value is available, Global defaults are used.
- Highest: StockIQ will use the higher of the two Calculated vs ERP lead times available.
- Lowest: StockIQ will use the lower of the two Calculated vs ERP lead times available.
- Fixed Value: The lead time will be a fixed value, which is provided in the rule.
Setting overrides with Edison
If you have the Edit Lead Time Overrides permission, you can ask Edison to create or replace overrides on either tab, for several suppliers, sites or items in one request. For example: "Set the shipping lead time to 448 days for item X from CME02 at sites 201 and 205", or "Create supplier-site lead time overrides for suppliers A, B and C into site X with a 30 day manufacturing lead time."
- Edison shows you a preview first, and saves nothing until you confirm it.
- Say which lead time you are changing: Admin, Manufacturing, Shipping, Expedited Shipping or Putaway. If you give one number without saying which, Edison asks you.
- An override sets every lead time method at once. The ones you don't mention keep what that item-site-supplier or supplier-site uses today, and the preview shows every value before you confirm.
- An item-site-supplier can have only one override in effect on any day. Edison won't add an override whose dates overlap another override on the same item-site-supplier. To replace an existing override, give the same effective date it has, or no effective date if it has none.
- After saving item-site-supplier overrides, Edison replans the affected items. Supplier-site overrides show up in your plans after the next scheduled refresh of StockIQ.
Deleting overrides by upload
To remove many overrides at once, click Upload..., check Delete Uploaded Overrides, and upload a file that lists the overrides to delete, in the same layout you use to add them.
- Row with a Date Effective- Deletes the override that is effective on that date for that item, site and supplier.
- Row with no Date Effective- Deletes the override if it is the only one for that item, site and supplier. If there is more than one, nothing is deleted.
- Supplier-site overrides- Work the same way, matched on supplier and site. Their upload calls the option Delete Uploaded Records.
Each row that deletes nothing is listed in the upload results with the reason, for example: 2 lead time overrides exist for item '101067' at site 'AZP' from supplier 'V3M' (effective: no date, 2026-08-12). Add a Date Effective to the row to choose which one to delete.
NOTE: When an override with no Date Effective has others beside it, a file can't pick it out. Delete it from the grid instead.